ISLAMABAD: National Electric Power Regulatory Authority (NEPRA) on Tuesday questioned sponsors of three 50MWp solar power projects over their requests for modification of previously determined tariffs, particularly with regard to the Commercial Operation Date (COD), Interest During Construction (IDC) and Return on Equity During Construction (ROEDC).
The three companies—Medrian Energy Limited, HNDS Energy Limited and Helios Power Limited—have filed separate petitions seeking amendments to their tariff determinations issued on February 21, 2020.
NEPRA had determined a levelised tariff of Rs5.6988 per kWh (US cents 3.6684 per kWh) for the three projects.
READ ALSO: Pakistan’s solar revolution: phase-two in full swing
During the hearing, Authority Members Amina Ahmed, Maqsood Anwar Khan and Ghulamullah Shaikh raised a series of questions with representatives of the project sponsors and the Central Power Purchasing Agency-Guarantee (CPPA-G) over the justification for the requested relief and its potential financial implications for electricity consumers.
The project sponsors maintained that they were seeking similar relief already extended to certain other power companies, arguing that delays in land acquisition and other project-related difficulties had prevented them from commencing construction within the originally envisaged timeframe.
They explained that the entire feasibility study of the projects had to be revised because of difficulties in acquiring land for the proposed sites, which affected the construction schedule.
The petitioners have requested NEPRA to withdraw the ten-month construction period linked to the Financial Close (FC) date of February 19, 2021, and instead allow the period to commence from the Construction Start Date (CSD) of June 14, 2022, as stipulated in the Energy Purchase Agreement (EPA).
They argued that tariff implementation and subsequent adjustments of IDC and ROEDC should be aligned with the actual commencement of construction and relevant project agreements.
The CPPA-G representative, however, maintained that the agency had taken action to ensure that the financial burden arising from delays was not passed on to electricity consumers.
He explained that the project companies had initially approached the Alternative Energy Development Board (AEDB) and the Government of Sindh, citing events of default and force majeure circumstances. Consequently, CPPA-G could not issue termination notices while those issues remained unresolved.
“After the issues of the power companies were sorted out with AEDB and the Sindh Government, CPPA-G issued notices of termination,” he added.
Member (Law) Ghulamullah Shaikh questioned the project sponsors whether NEPRA had made it clear in its original tariff determinations that delays in construction would not carry any financial implications for consumers.
A representative of the project companies acknowledged that the language of the original tariff determination conveyed the interpretation pointed out by the Authority members. However, he maintained that the companies could not commence construction because they did not have possession of the required project sites.
Under their petitions, the sponsors have sought modification of the reference tariff determinations to provide for a maximum construction period of ten months commencing from the Construction Start Date, as defined in the EPA.
They also requested that IDC at COD be calculated on the basis of actual debt drawdowns, within the overall debt approved by NEPRA, during the revised ten-month construction period.
Similarly, they have sought adjustment of ROEDC at COD based on actual equity injections, within the overall equity approved by the Authority, during the same period.
The petitions further seek a day-for-day extension of the permitted construction period to account for force majeure events.