RLNG shortage to risk winter power supply, ISMO warns

RLNG shortage to risk winter power supply, ISMO warns

Written by

in

ISLAMABAD: The Independent System Market Operator (ISMO) has warned that inadequate supplies of Re-gasified Liquefied Natural Gas (RLNG) to gas-fired power plants could expose the electricity system to stability risks during the upcoming winter, potentially resulting in increased load management.

In a letter addressed to Director General (Gas) Petroleum Division and Managing Director SNGPL, ISMO’s Executive Director System Operation Muhammad Zakria sought early arrangements for RLNG cargoes, highlighting concerns over the operational reliability of major gas-fired power plants in the absence of adequate fuel supplies.

The warning comes amid continuing uncertainty surrounding Pakistan’s LNG procurement arrangements, following rejection of expensive spot LNG bids for December 2026 and January 2027 and the issuance of a fresh tender by Pakistan LNG Limited (PLL) to secure additional cargoes for the same delivery windows.

READ ALSO: Power sector: gas output and use of RLNG slump

ISMO has specifically identified Haveli Bahadur Shah (HBS), Bhikki, Balloki and Punjab Thermal Power Limited (PTPL) as four power plants whose operation on High-Speed Diesel (HSD) has not remained stable in the past.

“In absence of adequate RLNG supplies to above-mentioned gas-fired power plants (GPPs), the power system is likely to face stability risks, potentially resulting in increased load management,” the letter states.

The system operator has therefore requested early arrangements for RLNG cargoes to ensure reliable operation of these plants and avoid additional pressure on the electricity system during winter.

Pakistan’s efforts to secure additional LNG supplies have encountered difficulties amid elevated international prices and uncertainty surrounding contracted supplies from Qatar.

Pakistan LNG Limited had issued an international tender on November 4, 2026, seeking two spot LNG cargoes of 140,000 cubic metres each, with a tolerance of plus or minus five percent, for delivery at Port Qasim, Karachi.

The first cargo was scheduled for December 14-16, 2026, while the second was required during January 9-11, 2027.

The initial deadline of November 6 was subsequently extended to November 10 following requests from international suppliers.

PLL received three bids from two international companies for the two cargoes. For the December delivery window, TotalEnergies Gas & Power Limited offered LNG at approximately USD 27.30 per million British thermal units (MMBtu), while QatarEnergy Trading LLC quoted USD 31 per MMBtu.

TotalEnergies emerged as the lowest evaluated bidder for December.

For the January 2027 cargo, TotalEnergies quoted approximately USD 27.10 per MMBtu and was declared the lowest evaluated bidder.

However, PLL decided not to proceed with the offers, considering the prices too expensive.

Following rejection of the bids, the state-owned company floated another tender on November 12, inviting international suppliers to submit fresh offers for the same two delivery windows.

The fresh tender seeks two LNG cargoes of 140,000 cubic metres each, on a Delivered Ex-Ship (DES) basis at Port Qasim, with bids due on November 18, 2026.

The renewed procurement exercise is aimed at securing additional LNG supplies for winter gas and electricity requirements, although the availability and price of cargoes remain uncertain.

The government has finalised a winter gas supply strategy under which it plans to procure 18 LNG cargoes for the four-month period from November 2026 to February 2027.

The target was reduced from an earlier proposed requirement of 24 cargoes, amid efforts to prioritise cheaper supplies under existing long-term LNG contracts with Qatar.

Under the strategy, Pakistan intends to maximise LNG deliveries under its two long-term agreements with Qatar while arranging additional supplies from the spot market and other sources if required.

The Petroleum Division has also been pursuing diplomatic engagement with Qatar to maximise deliveries under existing contracts.

However, disruptions to LNG supplies and uncertainty over the availability of additional cargoes have complicated winter fuel planning.

Earlier, the Petroleum Division had estimated that 24 LNG cargoes would be required to meet winter demand on the SNGPL network, including nine cargoes for the power sector and 15 for domestic consumption, with two additional cargoes envisaged as contingency supplies.

The revised procurement target of 18 cargoes has heightened the importance of ensuring adequate fuel allocation to power plants during periods of peak electricity demand.

Pakistan’s difficulties in securing LNG cargoes were also evident during September, when PLL repeatedly rejected spot market offers on account of high prices.

The company rejected an offer of approximately USD 26.97 per MMBtu from BP Singapore for a September 4-8 delivery window.

A subsequent offer of approximately USD 26.71 per MMBtu for September 8-12 was also rejected despite being lower than the previous quotation.

PLL subsequently floated another tender for a cargo scheduled for September 12-16 but received no bids from international suppliers.

The repeated procurement failures underscored the difficulties faced by Pakistan in securing LNG at prices acceptable to the government amid disruptions to Qatari supplies and elevated international market prices.

The shortage had already affected electricity generation, with RLNG-based power plants facing fuel constraints during the period.

ISMO’s latest warning is particularly significant because the four identified plants constitute an important component of Pakistan’s thermal generation fleet.

The system operator has specifically cautioned that their operation on HSD has not been stable in the past, limiting the reliability of switching to alternative fuel in the event of RLNG shortages.

Consequently, failure to arrange adequate RLNG supplies could reduce the availability of generation capacity during winter, when electricity demand patterns and gas requirements create additional operational challenges.

The warning also raises concerns about the implications of fuel shortages for system stability, particularly if several gas-fired plants become unavailable simultaneously.

ISMO has therefore emphasised the need for advance fuel arrangements rather than relying on emergency procurement after shortages emerge.

The letter has been copied to Abdul Rasheed Jokhio, Director General Gas, Ministry of Petroleum, Amer Tufail, Managing Director SNGPL, and Dr Masood Ahmad, Chief Executive Officer ISMO.

The communication highlights the growing coordination requirements between the Power Division, Petroleum Division, gas utilities and system operator to ensure adequate fuel availability for electricity generation.

The warning comes at a time when the government is attempting to manage electricity costs, improve power-sector efficiency and avoid excessive load shedding.

Any reduction in the availability of RLNG-based generation could require greater reliance on alternative fuels or other generation sources, potentially affecting the cost and operational efficiency of the electricity system.

If gas-fired plants cannot operate at required levels and alternative fuel arrangements remain unreliable, the system operator may have to resort to increased load management to maintain system stability.

Copyright Business Recorder, 2026